Owner decisions required
2
Overdue responses / actions
3
Open RFIs
5
2 technical · 3 commercial
Pending cost / time exposure
Owner decisions required
Decision log →COR-004 · Generator pad revision
BCM recommends Approve · GC proposed
Overdue
COR-005 · Window package upgrade
BCM recommends Revise
Open items
Technical vs commercial tracked separatelyTechnical — awaiting design response
RFI-012 Roof curb flashing at Unit 4B
Northline Architects
RFI-014 Corridor smoke damper type
Northline Architects
Commercial — awaiting BCM review / COR
RFI-015 Alternate tile at wet walls
COR-003 Additional site lighting Under review
Open site observations
Site visits →OBS-018 · Incomplete firestopping at shaft
Pinnacle GC
OBS-019 · Temporary railing at Stair 2
Unassigned
Cost & time
Approved changes to date
Pending (BCM assessed)
Pending (GC proposed)
Contract value
Recent owner decisions
Approved COR-002
Elena Park · Harbor Homes LLC
Rejected COR-001